Process
Installs Review: For upgrades and full systems
IGEMS
- LICENSE
Electrical Panel
- Take a photo of the Intime license code for customer backup
- Wires Pulled *if applicable
- UPS battery: move fuse to storage
- Labels on Enclosure, or in envelope if no enclosure
- MachMotion Label
- High Voltage Label
- Data Plate
- Yaskawa Sigma 7 drive sticker *if applicable
- Serial Number and Sales Order number sticker(not needed for knee mill)
- Panel Nuts on and tight
- Fan Metal Guard Installed and Screws tight *if applicable
Control QC
- Ensure all motors are connected in Rapid Path
- Remove old Mach4 folders on the (C:) drive
- Verify that the X15-41-01 MPG Pendent has been added to MachMotion Plugin if it is on the BOM
- Shut down the PC and Test Reset button in PC Boot Mode
- Restart the PC and make sure it turns on normally
- Confirm Correct icons are on the desktop
- This PC shortcut
- Recycle Bin shortcut
- MachMotion Programs and drives folder shortcut
- Backup Program shortcut
- Customer Documentation
- Teamviewer(Rename: MachMotion Support)
- Machine Type shortcut
- Post Processor (Alexsys, SheetCam, pronest.etc.)*if applicable
- VSI Device Manager
- Delete/relocate Desktop icons
- Relocate Desktop icons to MachMotion Programs and drives folder shortcut
- Sigma Win
- Adobe Acrobat
- RSI
- Pokey's
- GC Configurator
- Delete remaining icons from desktop
- Put a copy of the customers schematics on the USB thumb drive
- Put a MM 30 day timed license on control. https://support.machmotion.com/books/quality-control-and-testing-knowledge-base/page/machmotion-timed-license
- Remove old backups from backup file
- Run IO export from the production setup plugin... save as IO Final QC--C:\Mach4\DriveParameters\QC IO...Create QC IO folder if needed.
- Run MachMotion APPLICATION Backup and copy to USB and Server
- Empty Recycle Bin
- Delete downloads
- Remove Chrome account Login
Enclosure / Panel final steps
- Tighten ground screws on Yaskawa drives
- Blow Out the Enclosure
- Install Apollo III cover, Zip tie Apollo to frame and attach tag
- Print and install tag to remind them to install the fuse on the UPC
- Install Duct Cover*if applicable
- Install Grounding straps on the doors
- Take a final picture for Marketing with all the covers on*if applicable (not needed for knee mill)
- Print off updated customer schematics, Elec BOM and place in bag with. Zip tie to the panel
- ***Only for Chalmers and American Machine*** Print off connection list and put it with the schematics
- Disconnect Switch handle works/calibrated *if applicable
- Lock door and attach key to the door hinge*if applicable
- Check Fan Covers*if applicable
- Wipe Down Enclosure *if applicable
Control final steps / Packaging
- Install 8 position Phoenix connector
- Control top cover installed
- Clean
- Remove magnet labels
- Bag control
- Ship Keyboard tray assembly
- Pack Documentation Box
- Back covers and screws
- Keyboard and mouse
- Wi-Fi Antenna
- Wireless pendent
- Send INtime license card with the control in the document box
- Manuals
- Quick start tips
- MM promotional flyer
- Control Type Manual
- Motion Controller type *if applicable
- Machine Type Manual *if applicable
- Drive Type Manual *if applicable
- VFD Manual *if applicable
Job Final steps
- Log time in Odoo and closeout work orders
- Upload photos/video and rename final photo of the panel for marketing (“Final_PXL_2022...”) (not needed for knee mill)
- Enter post action reports in Odoo
- Enter changes to the QC tasks template