Nuke Process
Installs Review for upgrades and full systems:
- Notify the install department which system is ready for a review.
- Make any necessary changes indicated.
- Address any installation concerns.
Electrical Panel
- Take a photo of the Intime license code for customer backup.
- Wires Pulled *if applicable.
- UPS battery: move fuse to storage.
- Labels on Enclosure, or in envelope if no enclosure.
- MachMotion Label.
- High Voltage Label.
- Data Plate.
- Yaskawa Sigma 7 drive sticker *if applicable.
- Serial Number and Sales Order number sticker(not needed for knee mill).
- Panel Nuts on and tight.
- Fan Metal Guard Installed and Screws tight *if applicable.
Control QC
- Ensure all motors are connected in Rapid Path.
- Remove old Mach4 folders on the (C:) drive.
- Verify that the X15-41-01 MPG Pendent has been added to MachMotion Plugin if it is on the BOM.
- Shut down the PC and Test Reset button in PC Boot Mode.
- Restart the PC and make sure it turns on normally.
- Confirm Correct icons are on the desktop.
- This PC shortcut.
- Recycle Bin shortcut.
- MachMotion Programs and drives folder shortcut.
- Backup Program shortcut.
- Customer Documentation.
- Teamviewer(Rename: MachMotion Support).
- Machine Type shortcut.
- Post Processor (Alexsys, SheetCam, pronest.etc.)*if applicable.
- VSI Device Manager.
- Delete/relocate Desktop icons.
- Relocate Desktop icons to MachMotion Programs and drives folder shortcut.
- Sigma Win.
- Adobe Acrobat.
- RSI.
- Pokey's.
- GC Configurator.
- Delete remaining icons from desktop.
- Put a copy of the customers schematics on the USB thumb drive.
- Put a MM 30 day timed license on control. Timed License
- Remove old backups from backup file.
- Run IO export from the production setup plugin... save as IO Final QC--C:\Mach4\DriveParameters\QC IO...Create QC IO folder if needed.
- Run MachMotion APPLICATION Backup and copy to USB and Server.
- Empty Recycle Bin.
- Delete downloads.
- Remove Chrome account Login.
Enclosure / Panel final steps
- Tighten ground screws on Yaskawa drives.
- Blow Out the Enclosure.
- Install Apollo III cover, Zip tie Apollo to frame and attach tag.
- Print and install tag to remind them to install the fuse on the UPC.
- Install Duct Cover*if applicable.
- Install Grounding straps on the doors.
- Take a final picture for Marketing with all the covers on*if applicable (not needed for knee mill).
- Print off updated customer schematics, Elec BOM and place in bag with. Zip tie to the panel.
- ***Only for Chalmers and American Machine*** Print off connection list and put it with the schematics.
- Disconnect Switch handle works/calibrated *if applicable.
- Lock door and attach key to the door hinge*if applicable.
- Check Fan Covers*if applicable.
- Wipe Down Enclosure *if applicable.
Control final steps / Packaging
- Install 8 position Phoenix connector.
- Control top cover installed.
- Clean.
- Remove magnet labels.
- Bag control.
- Ship Keyboard tray assembly.
- Pack Documentation Box.
- Back covers and screws.
- Keyboard and mouse.
- Wi-Fi Antenna.
- Wireless pendent.
- Send INtime license card with the control in the document box.
- Manuals.
- Quick start tips.
- MM promotional flyer.
- Control Type Manual.
- Motion Controller type *if applicable.
- Machine Type Manual *if applicable.
Job Final steps
- Log time in Odoo and closeout work orders.
- Upload photos/video and rename final photo of the panel for marketing (“Final_PXL_2022...”) (not needed for knee mill).
- Enter post action reports in Odoo.
- Enter changes to the QC tasks template.