Install Timeline Overview
Monday
Open all boxes and examine all the parts, are the cables long enough? will the motors fit?
Push to get internet to the machine, watch old machine run and pull accel, decel, and speed parameters if you can before powering down.
If any mounting solutions look sketchy then try to get them done Monday so alternate solutions can be figured out before the end of the week if needed.
Pull the old electrical panel and mount the new one. recording the wiring of any special devices that need to be reused.
Tuesday
Get clarity and finalize your understanding of the Gcode for the post/ GC adapter
Start these, (you'll probably only only get progress on two. move the third to Wednesday)
- Mount all motors 
- pull cables through the machine
- Wire the cabinet
Wednesday
Finish These
- Mount all motors 
- pull cables through the machine
- Wire the cabinet
Power up the electrical cabinet.
Get basic motion on all axis if you can
Thursday
Test the I/O make sure it's wired correctly and everything functions
Start software setup
- Limit switches
- Calibrate (check the inspection form, sometimes it can save you time)
- Home and than setup softlimits
- Setup all other I/O
- Tune the servos if you need to
- setup the tool changer
Run a test cuts if you have time
square the gantry
Friday
Test the GC adapter/Post
Run test cuts,
Clean up the cabinet wiring
Train the customer
Finalize the GC adapter/post
Run production with them
Take Pictures and finish the redlines
back up drive parameters into the control and then back up the control
The 10 steps of an install
- Gather info from the old system
- Dismount the old stuff
- Mount the new stuff
- Run the cables
- Wire the new cabinet
- Test motion
- Config I/O
- Tune drives
- Test cuts
- Polish and document your work