Queue
Flow of Queue
- Operator either scans barcode or enters schedule and ID manually.
- If "Manual Add" is toggled on then before adding to queue, data is put into DRO's on the screen for the operator to edit. Editing done here doesn't change the actual CSV that the data is pulled from but changes the LUA table that has been loaded. Will keep changes until table gets reloaded. (EX: Compile Scripts, restart Mach)
- If operator enters 0 for the ID then all ID's in the schedule are loaded into the queue.
- Depending on the machine, different data is gathered and different functions are used to add the ID to the queue.
- The top item of the queue is always ran first. Items can be moved up and down to change their order.
- Pressing "Cycle Start" posts, loads and runs the GCode. Pressing "Post" only posts and loads the GCode. Each machine has their own unique Post function.
Important OEMParameters
CutoutFile: This holds the path to Cutout.csv
MaterialFile: This holds the path to Material.csv
JobPath: This holds the path to the folder containing WinCore's schedules.
SlabDecrement: Decrement taken off of a slab's width to represent it's actual size (.25)
SidelieDecrement: Decrement taken off of a sidelite's width to represent it's actual size (.125)
SawKerf: Kerf of the saw blade on the Jamb router
SawOffset: Offset of future cuts on the Jamb router after the first saw cut is made
MachineType: Choice of SLAB,EDGE or JAM. Allows you to say which machine profile is running on.